| |
Back Generator Installation | Up Construction Electrician Intermediate - Electricity handbook for electricians | Next Feeder Cable Connections |
3. The carbon monoxide gas present in the exhaust
of the engine is extremely poisonous. Under no
circumstances should this gas be allowed to collect in a
closed room; therefore, means have to be provided to
discharge the engine exhaust to the outdoors. Exhaust
can be vented by extending the exhaust pipe through the
wall or roof of the building. Support the exhaust pipe
and make certain that there is no obstruction and avoid
right-angle bends, ifpossible. Also, whenever possible,
arrange the exhaust system so that the piping slopes
away from the engine. In this way, condensation will
not drain back into the cylinders. If the exhaust pipe
should have to be installed so that loops or traps are
necessary, a drain cock should be placed at the lowest
point of the system. All joints have to be perfectly tight;
and where the exhaust pipe passes through the wall, you
have to prevent the discharged gas from returning along
the outside of the pipe back into the building. Exhaust
piping inside the building has to be covered with
insulation capable of withstanding a temperature of
1500°F.
After the generating units have been set in place
and bolted down, Builders then can proceed to erect the
building, using the necessary information provided by
the CEs.
Generator Set Inspection
After setting up a portable generator, your crew
must do some preliminary work before placing the
generator in operation. First, they should make an
overall visual inspection of the generator. Have them
look for broken or loose electrical connections, bolts,
and cap screws; and see that the ground terminal wire
(No. 6 AWG minimum ) is properly connected to the
ground rod/grounding system. Check the technical
manual furnished with the generator for wiring diagrams,
voltage outputs, feeder connections, and prestart
preparation. If you find any faults, you should correct
them immediately.
Generator Connections
When you install a power plant that has a dual-
voltage alternator unit, make certain that the stator coil
leads are properly connected to produce the voltage
required by the equipment.
Proper grounding is also a necessity for personnel
safety and for prevention of unstable, fluctuating
generator output.
INTERNAL LEADS.The voltage changeover
board permits reconnection of the generator phase
windings to give all specified output voltages. One end
of each coil of each phase winding runs from the
generator through an instrumentation and a static
exciter current transformer to the reconnection panel.
This routing assures current sensing in each phase
regardless of voltage connection at the reconnection
board assembly. The changeover board assembly is
equipped with a voltage change board to facilitate
conversion to 120/208 or 240/416 generator output
voltage. Positioning of the voltage change board
connects two coils of each phase in series or in parallel.
In parallel, the output is 120/208; in series, the output is
240/416 volts ac. The terminals on the changeover
board assembly for connection to the generator loads
are numbered according to the particular coil end of
each phase of the generator to ensure proper
connections.
Remember that you are responsible for the proper
operation of the generating unit; therefore, proceed
with caution on any reconnection job. Study the wiring
diagrams of the plant and follow the manufacturers
instructions to the letter. Before you start the plant up
and close the circuit breaker, double-check all
connections.
GROUNDING.It is imperative that you solidly
ground all electrical generators operating at 600 volts
or less. The ground can be, in order of preference, an
underground metallic water piping system, a driven
metal rod, or a buried metal plate. A ground rod has to
have a minimum diameter of 5/8 inch if solid and 3/4 inch
if pipe, and it has to be driven to a minimum of 8 feet. A
ground plate has to be a minimum of 2 square feet and be
buried at a minimum depth of 2 l/2 feet. For the ground
lead, use No. 6 AWG copper wire and bolt or clamp it to
the rod, plate, or piping system. Connect the other end of
the ground lead to the generator set ground stud.
The National Electrical Code® states that a single
electrode consisting of a rod, pipe, or plate that does not
have a resistance to ground of 25 ohms or less will be
augmented by additional electrodes. Where multiple rod,
pipe, or plate electrodes are installed to meet the
requirements, they are required to be not less than 6 feet
apart.
It is recommended that you perform an earth
resistance test before you connect the generator to
ground. This test will determine the number of ground
rods required to meet the requirements, or it may be
necessary to construct a ground grid.
3-5
|