Factors Affecting Fieldwork The surveyor must constantly be alert to the different conditions encountered in the field. Physical factors, such as TERRAIN AND WEATHER CONDITIONS, affect each field survey in varying degrees. Measurements using telescopes can be stopped by fog or mist. Swamps and flood plains under high water can impede taping surveys. Sights over open water or fields of flat, unbroken terrain create ambiguities in measurements using microwave equipment. The lengths of light-wave distance in measurements are reduced in bright sunlight. Generally, reconnaissance will predetermine the conditions and alert the survey party to the best method to use and the rate of progress to expect.The STATE OF PERSONNEL TECHNICAL READINESS is another factor affecting field-work. As you gain experience in handling various surveying instruments, you can shorten survey time and avoid errors that would require resurvey.The PURPOSE AND TYPE OF SURVEY are primary factors in determining the accuracy requirements. First-order triangulation, which becomes the basis or "control" of future surveys, is made to high-accuracy standards. At the other extreme, cuts and fills for a highway survey carry accuracy standards of a much lower degree. In some construction surveys, normally inaccessible distances must be computed. The distance is computed by means of trigonometry, using the angles and the one distance that can be measured. The measurements must be made to a high degree of precision to maintain accuracy in the computed distance.So, then, the purpose of the survey determines the accuracy requirements. The required accuracy, in turn, influences the selection of instruments and procedures. For instance, comparatively rough procedures can be used in measuring for earthmoving, but grade and alignment of a highway have to be much more precise, and they, therefore, require more accurate measurements. Each increase in precision also increases the time required to make the measurement, since greater care and more observations will be taken. Each survey measurement will be in error to the extent that no measurement is ever exact. The errors are classified as systematic and accidental and are explained in the latter part of this text. Besides errors, survey measurements are subject to mistakes or blunders. These arise from misunderstanding of the problem, poor judgment, confusion on the part of the surveyor, or simply from an oversight. By working out a systematic procedure, the surveyor will often detect a mistake when some operation seems out of place. The procedure will be an advantage in setting up the equipment, in making observations, in recording field notes, and in making computations.Survey speed is not the result of hurrying; it is the result of saving time through the following factors:1. The skill of the surveyor in handling the instruments2. The intelligent planning and preparation of the work3. The process of making only those measurements that are consistent with the accuracy requirementsExperience is of great value, but in the final analysis, it is the exercise of a good, mature, and competent degree of common sense that makes the difference between a good surveyor and an exceptional surveyor.Field Survey Parties The size of a field survey party depends upon the survey requirements, the equipment available, the method of survey, and the number of personnel needed for performing the different functions. Four typical field survey parties commonly used in the SEABEEs are briefly described in this section: a level party, a transit party, a stadia party, and a plane table party.LEVEL PARTY. The smallest leveling party consists of two persons: an instrumentman and a rodman. This type of organization requires the instrumentman to act as note keeper. The party may need another recorder and one or more extra rodmen to improve the efficiency of the different leveling operations. The addition of the rodmen eliminates the waiting periods while one person moves from point to point, and the addition of a recorder allows the instrumentman to take readings as soon as the rodmen are in position. When leveling operations are run along with other control surveys, the leveling party may be organized as part of a combined party with personnel assuming dual duties, as required by the work load and as designated by the party chief.TRANSIT PARTY. A transit party consists of at least three people: an instrumentman, a head chainman, and a party chief. The party chief is usually the note keeper and may double as rear chainman, or there may be an additional rear chainman. The instrumentman operates the transit; the head chainman measures the hori-zontal distances; and the party chief directs the survey and keeps the notes.STADIA PARTY. A stadia party should consist of three people: an instrumentman, a note keeper, and a rodman. However, two rodmen should be used if there are long distances between observed points so that one can proceed to a new point, while the other is holding the rod on a point being observed. The note keeper records the data called off by the instrumentman and makes the sketches required.PLANE TABLE PARTY. The plane table party consists of three people: a topographer or plane table operator, a rodman, and a computer. The topographer is the chief of the party who sets up, levels, and orients the plane table; makes the necessary readings for the determination of horizontal distances and elevations; plots the details on the plane table sheet as the work proceeds; and directs the other members of the party.The rodman carries a stadia rod and holds it vertically at detail points and at critical terrain points in the plotting of the map. An inexperienced rodman must be directed by the topographer to each point at which the rod is to be held. An experienced rodman will expedite the work of the party by selecting the proper rod positions and by returning at times to the plane table to draw in special details that he may have noticed.The computer reduces stadia readings to horizontal and vertical distances and computes the ground elevation for rod observations. He carries and positions the umbrella to shade the plane table and performs other duties as directed by the topographer. At times, the computer may be used as a second rodman, especially when the terrain is relatively flat and computations are mostly for leveling alone. |
||