Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  

 
Lightweight Concrete

Conventional concrete weighs approximately 150 lb per cubic foot. Lightweight concrete weighs 20 to 130 lb per cubic foot, depending on its intended use. Lightweight concrete can be made by using either gas-generating chemicals or

Figure 7-19.-Comparison of plain and prestressed concrete beams.

lightweight aggregates, such as expanded shale, clay, or slag. Concrete containing aggregates like perlite or vermiculite is very light in weight and is primarily used as insulating material. Light-weight concrete is usually classified according to its weight per cubic foot.

Semi-lightweight concrete has a unit weight of 115 to 130 lb per cubic foot and an ultimate compressive strength comparable to normal concrete. Sand of normal weight is substituted partially or completely for the lightweight fine aggregate.

Insulating lightweight concrete has a unit weight ranging from 20 to 70 lb per cubic foot, and its compressive strength seldom exceeds 1,000 psi. This type of concrete is generally used for insulating applications, such as fire-proofing. Structural lightweight concrete has a unit weight up to 115 lb per cubic foot and a 28-day compressive strength in excess of 2,000 psi. This type is used primarily to reduce the dead-load weight in concrete structural members, such as floors, walls, and the roof section in high-rise structures.

Heavyweight Concrete

Heavyweight concrete is produced with special heavy aggregates and has a density of up to 400 lb per cubic foot. This type is used principally for radiation shielding, for counterweights, and for other applications where higher density is desired. Except for density, the physical properties of heavyweight concrete are similar to those of normal- or conventional-weight concrete.

TILT-UP CONSTRUCTION

Tilt-up concrete construction is a special form of precast concrete building. This method consists basically of jobsite prefabrication, in which the walls are cast in a horizontal position, tilted to a vertical position, and then secured in place. Tilt-up construction is best suited for large one-story buildings, but it can be used in multistory structures. Usually, multistory structures are built by setting the walls for the first story, placing the floor above, then repeating the procedure for each succeeding floor. An alternate method is to cast two- to four-story panels.

The wall panels are usually cast on the floor slab of the structure. Care must be exercised to ensure the floor slab is smooth and level and that all openings for pipes and other utilities are temporarily plugged. The casting surface is treated with a good bond-breaking agent to ensure the panel does not adhere when it is lifted.

Reinforcement of Tilt-Up Panels

The steel in a tilt-up panel is set in the same manner as it is in a floor slab. Mats of reinforce-ment are placed on chairs and tied as needed. Reinforcement should be as near the center of the panel as possible. Reinforcing bars are run through the side forms of the panel. When welded wire fabric or expanded wire mesh is used, dowel bars are used to tie the panels and their vertical supports together. Additional reinforcement is generally needed around openings.

The panel is picked up or tilted by the use of PICKUP INSERTS. These inserts are tied into the reinforcement. As the panel is raised into its vertical position, the maximum stress will occur; therefore, the location and number of pickup inserts is extremely important. Some engineering manuals provide information on inserts, their locations, and capacities.

Tilt-Up Panel Foundations

An economical and widely used method to support tilt-up panels is a simple pad footing. The floor slab, which is constructed first, is NOT poured to the perimeter of the building to permit excavating and pouring the footings. After the panel is placed on the footing, the floor slab is completed. It may be connected directly to the outside wall panel, or a trench may be left to run mechanical, electrical, or plumbing lines.

Another method that is commonly used, as an alternative, is to set the panels on a grade beam or foundation wall at floor level. Regardless of the type of footing, the panel should be set into a mortar bed to ensure a good bond between the foundation wall and the panel.







Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business