Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Chapter 12 - Boilers
Back | Up | Next

tpub.com Updates

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Back ] Home ] Up ] Next ]

CHAPTER 12 BOILERS

The most common type of boiler in the NCF is the scotch marine. "Scotch marine" is a generic term that identifies a boiler with a furnace, which forms an integral part of the boiler assembly. This configuration allows for compact construction requiring only a small space for the capacity produced. Scotch marine boilers are package units consisting of a pressure vessel, burner, controls, draft fan, and other components assembled into a fully factory fire-tested unit. This provides an engineered unit equipped for quick installation and connection to services. As a first class petty officer, you will supervise personnel in the installation, operation, and maintenance of boilers. As a chief petty officer, you will be responsible for the general management of these plants. This chapter provides insight into many skills that you must develop to be a proficient supervisor/manager of a boiler plant.

INSTALLATION OF BOILERS

When you are preparing to install a boiler, consider three basic factors-site location, accessories, and fittings. This section discusses each of these items. Proper installation of a boiler helps to ensure succesful operation. Always refer to the manufacturer's manuals, and follow your prints and specifications closely. By being thorough in your planning and execution of plans, you can prevent many future problems for operators and maintenance personnel.

SITE LOCATION

Give careful consideration to site location for the construction of a boiler plant. Primarily, the cost in materials, manpower, and equipment is the most important factor effecting this selection. These costs can usually be reduced by locating the plant site as close as possible to the largest load demand facility, such as a galley or laundry.

Location

When selecting a site for boiler installation, you must consider the availability of the following:

. Water

. Electricity

. Fuel

. Natural site drainage

Attempt to avoid high pedestrian and vehicle traffic areas for safety reasons. Another item to consider is noise level. Noise pollution may cause discomfort for personnel, especially if the site being considered is adjacent to a berthing area.

These are factors you must consider when you become involved in selecting a boiler plant site. Each situation may include all, part, or more than these factors. You must look at each installation and evaluate the needs of that job.

Boiler Foundation

Constructing the foundation or platform a boiler sits on requires skilled engineering and development. Follow the manufacturer's specifications. Boilers may vary in wet weight from 1.5 tons to more than 20 tons. A substantial foundation that can withstand the weight and absorb vibration is essential.

Reinforced concrete slabs with runners provide for placing and anchoring the boiler. The runners should provide a level, uniform support and be of sufficient height to allow for maintenance and the installation of piping under the boiler. A raised platform also provides easier access for boiler room cleanup.

Generally, a sump in the slab between the runners provides a catchment area for boiler blowdown or draining of the boiler. This sump drains from the building to a suitable dispersal point.

Boiler Room

When considering the requirements of sheltering a boiler, you must ensure there is enough room for the boiler and all of the accessory equipment. This accessory equipment may include condensate tanks and pumps, chemical feeders, water makeup tanks and feeders, and blowdown tanks.

The boiler room must also be large enough to allow for boiler maintenance, for retubing, and for removing and replacing the boiler. The tube length of a boiler maybe from 2 feet 6 inches to at least 10 feet, and possibly longer. To simplify the removal of the tubes, ensure the boiler room is long enough or have a door located behind the boiler. The most important thing to check is the manufacturer's specifications, which provides the proper dimensions for locating the boiler.

Fresh air inlets and louvers allow fresh air to enter and move across the boiler area. This fresh air entering the boiler room removes excess heat and provides adequate makeup air for combustion.

When planning for boiler room construction, you must always consider boiler requirements, maintenance requirements, and manufacturer's recommendations.