The steps taken by the instrumentman and the rodman
are as follows: 1. The instrumentman determines the center-line
cut
by subtracting 350.7 ft from 364.0 ft to get
the cut, or 13.3 ft.
2. The rodman holds at the center line for a
check. The rod should-read 369.3 (the HI) minus 364.0,
or 5.3 ft.
3. The instrumentman calls to the rodman, "Cut
13.3 feet."
4. The rodman computes d= 20+(1
x 13.3) = 33.3 as he walks to the
left.
5. As he approaches about 30.0 ft from the center
line, he estimates that the ground has a fall of
4 ft. Therefore, he computes the new cut as
13.3 4.0, or 9.3 ft.
This means a new d of
20 + (1 x 9.3) = 29.3 ft.
6. The rodman sets up the rod 29.3 ft from the
center line, as measured by metallic tape.
7. The instrumentman reads 10.1 on the rod and
computes the new cut as
369.3 (350.7 + 10.1), or 8.5 ft.
NOTE: Here you can also use the grade rod and
ground rod values as explained earlier; the new
cut then will be
18.6 10.1 = 8.5 ft.
Refer back to figure 14-36.
8. The instrumentman calls, "Cut 8.5," to the
rodman.
9. The rodman computes
d = 20 + (1 x 8.5) = 28.5 ft.
He knows, therefore, that 29.3 ft from the center line
is too far out.
10. Figuring that the ground rises about 0.1 ft
between 29.3 left and 28.5 left, the rodman calculates
that the more nearly correct cut will be
8.5 + 0.1, or 8.6 ft.
11. By using this cut, the rodman calculates the
new d as
20 + (1 x 8.6),
and sets the rod at 28.6 ft left.
12. The instrumentman reads and
computes the new cut as
369.3 (350.7 + 10.0) =
10.0 on the rod
8.6 ft.
13. The instrumentman calls, "Cut 8.6," to the
rodman.
14. The rodman sees that the actual cut of 8.6 ft
agrees with his estimated cut of the same, and calls,
"Cut 8.6 at 28.6," to the instrumentman.
15. The instrumentman checks d =
20 + (1 x 8.6) = 28.6, signals the
rodman, "Good," and makes the following entry into the field book:
16. The rodman marks a stake with 15 + 00 and C86
and drives it in the ground at 28.6 ft left.
More often, slope stakes may be set by using a
hand level. Their distances out are generally measured
to the nearest half or tenth of a foot. If
a slope stake is placed in an offset position, the offset
distance is also marked on the stake so the equipment
operator is not confused about its actual
location. Slope stakes are seldom used in areas
requiring less than 2 ft of cut or fill.
Curb and Gutter Stakeout
For a thoroughfare that will have a curb and gutter,
these items are usually constructed before the
finish grading is done. The curb constructors obtain
their line and grade from offset hubs like those
described previously. Guided by these, the earthmovers
make the excavation for the curb, the
formsetters set the forms, and the concrete crew
members pour, finish, and cure the curb. Once
the curb has been constructed, shaping the
subgrade to correct subgrade elevation and laying
the pavement to correct finished grade is simply
a matter of measuring down the correct distance
from a cord stretched from the top of one
curb to the top of the curb opposite.
|
|