Pavement Stakeout Pavement stakeout will depend on the type of paving
equipment used. Steps in the method commonly
used for paving concrete highways are as
follows:
1. Set a double line of steel side forms, equipped
with flanges that serve as tracts for traveling
paving equipment.
2. Fill the space between the forms with concrete
poured from a concrete paving machine (commonly
called just a paver).
3. Spread the concrete with a mechanical spreader
that travels on the flanges of the side forms.
4. Finish the surface with a finisher, a machine
that also travels on the side forms.
The line-and-grade problemthat is, the layout
or stakeout problemconsists principally of
setting the side forms to correct line with the upper
edges of the flanges at the grade prescribed for
the highway. If the finished grade shown on the
plans is the center-line grade, then the forms are
set with tops at the center-line grade less the crossfall.
If the design elevations are shown for points
other than those on the center line, the form
elevation is related to the design points as indicated
by the typical section.
Stakeout maybe done by setting a line or lines of
offset hubs, as previously described. Some-times, however,
a line of hubs is driven along the line
the forms will occupy and driven to grade elevation
less the depth of a side form. The forms are
then set to the line and the grade by simply placing
them on the hubs.
Concrete paving is also done by the slip form method
in which, instead of a complete double line
of forms, a sliding or traveling section of formwork
is an integral part of the spreading and finishing
machinery. The machinery is kept on line and
the pavement finished at grade by a control device
or devices. The line control device usually follows
a wire stretched between rods that are offset
from the pavement edge.
Forms are not usually used in asphalt paving. Asphalt
paving equipment, in general, is designed to
lay the pavement at a given thickness, following the
fine-graded subgrade surface. The manner in which
a given piece of equipment is kept on line varies,
and the stakeout for equipment varies accordingly.
STRUCTURAL SURVEYS
A STRUCTURAL survey is one that is part of
the chain of human activities that will bring a
structure, such as a building, a bridge, or a pier into
existence.
Earthwork
As when a highway is built, the first major step
in the construction of a structure is usually the
rough gradingthat is, the earthmoving needed
to bring the surface of the site up to, or down
to, the approximate specified rough grade. The
stakeout for rough grading is commonly done
by the GRID method. The area to be graded, which
is shown, along with the prescribed finish grade
elevation on the site or plot plan is laid off in
25-, 50-, or 100-ft grid squares. The elevation at
each corner point is determined; the difference between
that and the prescribed grade elevation is
computed; and a grade stake is marked with the
depth of cut or fill; then the stake is driven into
the ground at the point.
|
|